Update shared on 29 Sep 2025
A little update:
The latest news on the Zancudo and Aguablanca projects indicates that while Zancudo is meeting its immediate operational milestones, a key piece of infrastructure at Zancudo is slightly delayed, and the major catalyst for Aguablanca is also now projected for a later date in the timeline.

Summary for Zancudo: The company has successfully moved into the production phase and is generating revenue, checking off two major H2 2025 catalysts. However, the completion of the new, higher-capacity processing plant has shifted from Q4 2025 to Q1 2026.
The Zancudo project is currently in a two-phase production ramp-up:
1. Early Production Phase (Current)
- Mining Operations: Denarius Metals officially commenced mining activities at the Zancudo Project in April 2025.
- First Revenue/Shipments: The company recorded its first revenues and completed its first shipment of high-grade crushed ore to Trafigura in June 2025. Shipments are expected to increase in frequency and quantity as mining operations ramp up.
- Processing: During this early phase (which is expected to run until the new plant is operational), the mined material is being crushed on-site and then shipped to a local port for sale, generating early cash flow.
2. Full Processing Plant Operation
- Completion of Construction: The company's new 1,000 tonnes per day (tpd) processing plant is scheduled to be fully constructed and operational by the first quarter of 2026 (or Q4 2025 in some previous guidance).
- Full Production: Once the new plant is operational, the company will begin processing the ore to produce high-grade gold-silver concentrates on-site for delivery to Trafigura under their long-term offtake contract. The goal is to reach the full 1,000 tpd capacity over time.
In summary, they are already in production with early shipments and revenue generation, while the final large-scale processing facility is expected to be completed and fully operational in early 2026.
The company's plan involves an early production phase ramping up to full production. Based on the public information available from the Preliminary Economic Assessment (PEA) and company updates, here is a summary of the expected production profile and financial metrics:

Other FAQ.



Disclaimer
The user RockeTeller has a position in NEOE:DMET. Simply Wall St has no position in any of the companies mentioned. Simply Wall St may provide the securities issuer or related entities with website advertising services for a fee, on an arm's length basis. These relationships have no impact on the way we conduct our business, the content we host, or how our content is served to users. The author of this narrative is not affiliated with, nor authorised by Simply Wall St as a sub-authorised representative. This narrative is general in nature and explores scenarios and estimates created by the author. The narrative does not reflect the opinions of Simply Wall St, and the views expressed are the opinion of the author alone, acting on their own behalf. These scenarios are not indicative of the company's future performance and are exploratory in the ideas they cover. The fair value estimates are estimations only, and does not constitute a recommendation to buy or sell any stock, and they do not take account of your objectives, or your financial situation. Note that the author's analysis may not factor in the latest price-sensitive company announcements or qualitative material.